Hanford Viaduct

Edition: Spring 2025
hanford viaduct

Only 112 of the 978 pre-cast concrete girders remain for the build out of the Hanford Viaduct. This month, crews will begin placing the remaining girders that will span over the San Joaquin Valley Railroad. Crews are also placing concrete to form the parapet and derailment walls at the southern end of the structure that spans over State Route 198. More than 40,300 cubic-yards of concrete have been placed to date at the Hanford Viaduct. When complete, the Hanford Viaduct will span 6333-feet long and will take high-speed trains over the highway or to the Kings/Tulare Regional Station.