Closure
MULTIPLE CLOSURES:
- Lane and shoulder closures along Belmont Avenue, between Parkway Drive and east of the northbound SR 99 on-ramp;
- Closure of the southbound SR 99 off-ramp to Belmont Avenue.
Work is scheduled to begin Wednesday, July 26 through Monday, Aug. 28, 2023.
Detour
Signage will be in place to direct traffic.
Description
Kings County, Calif. – The California High-Speed Rail Authority (Authority), in cooperation with design-build contractor Dragados-Flatiron Joint Venture (DFJV), announces intermittent traffic impacts along Grangeville Boulevard, Seventh Avenue, and Lacey Boulevard in Kings County to transport pre-cast girders to the Hanford Viaduct. Work is scheduled from 4 a.m. to 2 p.m. through Thursday, July 20, 2023.
This work is part of Construction Package 2-3 (CP 2-3), the 65-mile stretch of high-speed rail between East American Avenue in Fresno County and one-mile north of the Tulare-Kern County line.
All construction activities and schedules are subject to change. The California High-Speed Rail project is considered a critical infrastructure sector, and as the project continues, staff, contractors and construction workers are following specific guidelines to ensure the health and safety of all employees due to the COVID-19 pandemic.
This schedule is subject to change. For up-to-date information please visit BuildHSR.com or the Caltrans Quickmap. Traffic laws will be fully enforced and commuters are expected to be aware of the surrounding activities, remain alert and watch for construction vehicles and personnel. The public is asked to drive carefully and be extra cautious while traveling though the construction areas.
Contact
Augie Blancas
California High-Speed Rail
(559) 720-6695
augie.blancas@hsr.ca.gov
Ramiro Diaz
California High-Speed Rail
(559) 577-2246
ramiro.diaz@hsr.ca.gov