At Avenue 11, just east of Road 30 ½, the abutments for the overpass have been completed and bridge girders have been set. Crews are now beginning to form the bridge deck for this structure, which will take traffic over the high-speed rail alignment. A crane is seen lifting pre-cast concrete bridge deck panels onto the structure where they are carefully guided into place. Once the deck panels have been installed, the ironworkers will lay the deck steel. Next, carpenter and laborer crews will move in to form the edge of the deck and prepare for a concrete pour. Other crews have finished the block walls, which will retain the earthen embankment extending from the abutments.