At Avenue 15, just east of Road 29, the drilling operation finished the western abutment and has moved east of the tracks to begin drilling the eastern abutment. A carpenter crew and ironworkers have mobilized on the west abutment footing; setting forms and installing reinforcing bar. Column forms for a bent (a bent is composed of a column and cap element that the girders rest on) will be removed next and falsework set around the columns. Once the falsework is complete, the forming of the bent cap will begin.