Avenue 15 Grade Seperation

Ironworkers have been hard at work setting forms and installing reinforcing rebar on the west abutment footing of the Avenue 15 overpass in Madera County. Towards the east side of the structure, drilling for the cast-in-place wall foundations that extend from each abutment is also underway. Columns for a bent have been poured and falsework will be constructed next to form the bent cap that will support the superstructure elements, such as the pre-cast girders and concrete deck.