Cedar Viaduct

Edition: November 2019
Project: Cedar Viaduct

This week, nighttime closures kicked off on State Route 99 as crews began the placement of precast concrete girders over the highway to connect the Cedar Viaduct. Near the south abutment of the structure, Martinez Steel has completed tying rebar, and crews are now placing concrete for the stems and soffit of the bridge deck. When complete, the Cedar Viaduct will be approximately three quarters of a mile long.