At the Conejo Viaduct, crews continue to work on the edge beams of the pergola structure. To the south of the future pergola, the forms have already been stripped for the edge beams. Traveling north, crews continue to place concrete to form the edge beams. More than 1,000 cubic yards have been placed to date.