Skip to Main Content

CP 2-3: Jackson Avenue

Crews are working and close to completing work on the Melga Canal near the future Jackson Avenue overcrossing. Earlier this month, crews poured more than 200 cubic yards of concrete to form transition ends which include wing walls, head walls, and concrete lining. Once the concrete culvert is complete, it will achieve both sustaining consecutive water flow and having embankment dirt placed overhead.