CP 4: Wasco Viaduct

Edition: Fall 2022
Project: Wasco Viaduct
Wasco Viaduct November 2022

Ironworkers are working hard tying rebar across the Wasco Viaduct. Crews are tying rebar to form the deck on the northern and southern portions of the pergola. Concrete has also been placed to form the edge beams of the Wasco Viaduct where girders were installed. More than 1,500 cubic yards of concrete were placed to form the two remaining edge beams and more than 1,400 cubic yards will be needed for the two remaining decks of the structure.