Skip to Main Content

Road 27 Grade Separation

At the northern end of Construction Package 1, the overcrossing for Road 27 in Madera County continues to take shape as crews complete the support structures for the coming placement of concrete girders. The first two girders to be placed across the railroad tracks are currently scheduled during a night time closure of the rail line at the end of this month, with two more girders scheduled in late September. A total of 28 girders will be set to create the foundation for the crossing superstructure with the deck tentatively scheduled to be poured in January. As soon as utility relocation begins, embankment work will also commence. The bridge will be more than 600 feet long with the longest span stretching 198 feet.