At the northern end of Construction Package 1, large concrete girders are being set for the overcrossing at Road 27 in Madera County. The first two girders were placed across the railroad tracks during a night time closure in late August, while the second two girders are currently scheduled to be set in late September. A total of 28 girders will create the foundation for the crossing superstructure, with the deck tentatively scheduled to be poured early next year. Following utility relocation, embankment work can also begin. Ultimately, the bridge will be nearly 700 feet with frontage roads providing access along the sides to local homes.