The southbound State Route 99 Clinton Avenue and Golden State Boulevard off-ramps are now open to traffic. Work is continuing on the northbound Clinton Avenue on-ramp, which is scheduled to open when northbound traffic on SR 99 is switched to the new highway alignment in the coming weeks. At the Ashlan Avenue Bridge, crews are continuing to form and subgrade the bent caps for the structure’s abutments. Falsework construction for the new bridge has also begun. A portion of SR 99 is being realigned about 100 feet to the west to make way for the high-speed rail alignment.