Ninth Avenue Viaduct

Ninth Avenue Viaduct

At Ninth Avenue, crews continue to construct the falsework for the superstructure of the future high-speed rail structure. Next, crews will tie rebar for the soffit of the structure, in preparation of a concrete placement. Both structures will carry high-speed trains...
Peterson Road Bridge

Peterson Road Bridge

At Peterson Road, concrete for the stem walls has been placed. Currently, crews are installing post-tensioning strands which reinforces the concrete. Crews will begin pre-stressing the bridge deck in the coming weeks. When complete, the structure will be more than...
Pond Road Viaduct

Pond Road Viaduct

In August, crews placed 431 cubic-yards of concrete to form the deck of the Pond Road Viaduct. Feet Long Feet...
Poso Creek Viaduct

Poso Creek Viaduct

On Oct. 28, 2020, the California High-Speed Rail Authority announced the completion of Poso Creek Viaduct in Kern County, the first completed structure in the 22-mile segment of high-speed rail from the Tulare-Kern county line to Poplar Avenue in Kern County known as...
Road 27 Grade Separation

Road 27 Grade Separation

The California High-Speed Rail Authority, in collaboration with design-build contractor Tutor-Perini / Zachry / Parsons, completed the Road 27 grade separation in Madera County as of August 20, 2021. The Road 27 grade separation is located between Avenue 17 and Club...