Crews continue superstructure work on the Fowler Avenue Grade Separation. Crews have formed and placed concrete for the diaphragms of the structure, the portion of the bridge that helps support the load of the bridge deck between the abutments and set girders. 114 deck panels will be installed at Fowler Avenue. Ironworkers will install rebar for the deck of the structure at Fowler Avenue in the coming weeks.