Crews continue superstructure work on the Elkhorn Avenue Grade Separation. Crews have formed and placed concrete for the diaphragms of the structure, the portion of the bridge that helps support the load of the bridge deck between the abutments and set girders. 114 deck panels have been installed there. Ironworkers are now installing rebar for the deck of the structure at Elkhorn Avenue.