At the northern end of Construction Package 1, a total of 28 girders have been set to form the foundation for the crossing superstructure. Currently, crews are beginning construction of diaphragms that will connect the girders to one another along the sides. They’ll also start closure pours which will connect the girder sections together. After some additional utility relocation, embankment work will also begin. Ultimately, the bridge will be nearly 650 feet with frontage roads providing access along the sides to local homes.