Crews are conducting utility relocations along Golden State Boulevard including installing a new sewer line in preparation for relocating the roadway to the west. The high-speed rail line will be constructed between the new roadway and existing freight...
Only 112 of the 978 pre-cast concrete girders remain for the build-out of the Hanford Viaduct. In June 2025, crews will begin placing the remaining girders that will span over the San Joaquin Valley Railroad. Crews are also placing concrete to form the parapet and...
In May 2023, the California High-Speed Rail Authority (Authority) and contractor Dragados-Flatiron Joint Venture (DFJV) announced the completion of the Idaho Avenue grade separation. The overcrossing spans 205 feet and is 40 feet wide. The structure will take traffic...
On Sept. 15, 2022, the California High-Speed Rail Authority (Authority), in collaboration with Dragados-Flatiron Joint Venture, announced the opening of the Jackson Avenue overcrossing, a grade separation and the first completed high-speed rail structure in Kings...
The California High-Speed Rail Authority announced on November 2, 2023, the completion of the Kansas Avenue overcrossing, the ninth high-speed rail structure to be completed this year. Designed and constructed by Dragados-Flatiron/Joint-Venture (DFJV), the Kansas...